Bags and bags of cement. Piles and piles of sand. Mr Spade joined us this night, ready to rummm~mble~!

Mr Spade having tea with DJ C-man and Emcee Sandz!


Doors detached themselves, tiles split in perfect sizes. Everything was everywhere. Everyone was lining up in orderly lines, waiting for their turn to be part of the big project!



A layer of special concoction was applied to the bathroom, enabling selected tiles to be Spidertiles for the very first (and only) time after their escape from the tile factory!



Stay tuned for more pictures - in a couple of minutes, promise! -


Dar (aka Spectro)

No comments:

- Renovation Milestones -

  • 03 Nov 08 - Reno completed! Hand over!
  • 27 Oct 08 - Kitchen Carpentry completed
  • 20 Oct 08 - TV Feature Wall completed
  • 16 Oct 08 - Painting completed
  • 11 Oct 08 - MBR Wardrobe completed
  • 11 Oct 08 - MBR Toilet cabinet completed
  • 10 Oct 08 - MBR Platform completed
  • 08 Oct 08 - Shoe Cabinet/Settee completed
  • 08 Oct 08 - Bdrm 2 Wardrobe completed
  • 03 Oct 08 - Lightings installed
  • 30 Sept 08 - Window Grills up
  • 22 Sept 08 - Tiling completed
  • 21 Sept 08 - Toilet Overlay completed
  • 20 Sept 08 - Kitchen Bases completed
  • 12 Sept 08 - False Ceiling completed. Reno officially starts.
  • 10 Sept 08 - Aircon Trunking completed, Sand and Tiles delivered
  • 08 Sept 08 - Reno Loan approved